What are the alternatives to the Gantt chart to predict the web development process?

In addition to the General use of DG and obvious advantages, this method contains a number of grave shortcomings (for example, described here).
Does anyone have real experience with the alternatives?
July 2nd 19 at 17:32
2 answers
July 2nd 19 at 17:34
The Gantt chart is not a prediction method of the process is the visualization tool.
On the question of the limitations of classical project management on the critical path method and the way to overcome recommend reading the work of the Goldratt "Critical chain". (Critical chain method is an alternative to the critical path)
Critical chain and critical path, it is in principle different things. KP is a sequence task changes in which result in changes of the whole project, and KC is a method of planning buffers. - Breana.Stiedema commented on July 2nd 19 at 17:37
July 2nd 19 at 17:36
There are plenty of approaches to project management (see the list here- mahamba.com/ru/glossary?field_article_type_value%5... ) of the alternatives, look in the direction of Agile frameworks.

But really, is not so much to be upset about DG, because the article is misleading, there is such thing as a pert estimate, the buffers, the theory of critical chain, etc., which allow more accurate planning. And indeed the question itself is not entirely correct set - any approach (which is just a tool) there is a place for planning, so there will always be variances, and indeed the name "plan" is that how you would like to do a "fact," how did.

Find more questions by tags Project managementInfographicsTime management